Cost overview P01-P25 · PALT Nordreisa
P01-P25 · AP01-AP10

Cost overview: the 25 inputs

Main cost items per project, with the basis behind each figure and what is still open.

Working total (13 of 25 counted)
4,391.6 MNOK
Sum of working estimates, mostly midpoints
Range for the same 13
~2,950-7,220 MNOK
Low to high case, checked 20 Sep 2026
Annual income at full operation
~409.6 MNOK
Indicative, not a forecast
Jobs (working range)
247-1,015
Upper end not yet explained
  • 4,391.6 MNOK is the sum of working estimates, not a budget and not a funding need. It counts 13 of the 25 inputs, mostly at the midpoint of their range. The other 12 are studies, duplicates, programmes or already part of P10.
  • Kvænnes (P10) is 63 % of the total. The total is in practice the Kvænnes figure.
  • Not calculated: the tunnel and mountain-hall system around Nordkjosnes (about 7 km of tunnel in the concept drawings). By PALT's own unit rate for a narrow tunnel the tunnel bore alone is about 1,400-2,100 MNOK. See P12.
  • Kvænnes needs public or non-commercial capital. Modelled EBITDA is 11.1 MNOK/year against about 149 MNOK/year needed for an 8 % return on the private capital. The gap is about 138 MNOK/year in the base scenario.
  • Yellow boxes marked 'Cost check' are a bottom-up control made 20 Sep 2026. They use stated assumptions and market references, not quotes.

AP01 · Sandnes Fjord destination

Working estimate: ~370 MNOK
Sandnes Fjord Camping & Domes
P01In total

Sandnes Fjord Camping & Domes

Sandnes Fjord

Working estimate
~220 MNOK
Range
120-320 MNOK
Income / yr
~35 MNOK
Jobs
15-35
Maturity
3/5

Main cost items (amounts not yet split)

  • Dome lodges along the ridge boardwalk
  • Reception, restaurant and rooms by the E6
  • Fjord-side spa and sauna
  • Harbour, small-boat and kayak access
  • Roads, parking, water and sewage

Basis: Slide 27: cost frame 120-320 MNOK. Working estimate is the midpoint. Not yet split by item.

Cost check 20 Sep 2026. The frame also mentions the spa and an indoor water park (see P02), which is priced separately at ~150. A bottom-up check of P01 without the water park gives roughly 140-600 MNOK (base ~280).

Open project page →

Spa, Sauna & Waterpark
P02In total

Spa, Sauna & Waterpark

Sandnes Fjord

Working estimate
~150 MNOK
Range
60-250 MNOK
Income / yr
~25 MNOK
Jobs
8-25
Maturity
3/5

Main cost items (amounts not yet split)

  • Dome water park (badeland)
  • Long water slide from the reception building
  • Spa, sauna and soaking pools
  • Sea-water heat exchange for pool heating
  • Building services and water treatment

Basis: Illustrative working estimate with no slide source. Sauna first, full park later.

Cost check 20 Sep 2026. Comparable Norwegian water parks cost about 130-142 MNOK (Kristiansand, Hovden). Bottom-up check for this concept: roughly 130-300 (base ~190). The low end of 60 is not supported by references.

Open project page →

AP02 · Food, agriculture and learning

Working estimate: ~210 MNOK
Greenhouse & Aquaponic Dome
P03In total

Greenhouse & Aquaponic Dome

Veibakken

Working estimate
~185 MNOK
Range
45-360 MNOK
Income / yr
~55 MNOK
Jobs
15-45
Maturity
2/5

Main cost items

  MNOK
Affordable first phase (pilot) 45-80
Full first build 120-250
Extended long-term version 250-360

Basis: Slide 39. The working estimate 185 is the midpoint of the full first build. The next decision is a pilot of 1,500-3,000 m2.

Cost check 20 Sep 2026. The source is confirmed. Income of 55 MNOK/year here and 20 MNOK/year in P15 may overlap (same food sales) and should be separated.

Open project page →

Growth Circle in the Dome Environment
P15In total

Growth Circle in the Dome Environment

Veibakken / Nordreisa

Working estimate
~25 MNOK
Range
8-60 MNOK
Income / yr
~20 MNOK
Jobs
8-25
Maturity
2/5

Main cost items (amounts not yet split)

  • Processing and food brand
  • Plots, courses and demonstration field
  • Distribution and market channels

Basis: Illustrative processing/brand estimate. The greenhouse investment sits in P03 and is not duplicated here.

Cost check 20 Sep 2026. Income of 20 MNOK/year may overlap with P03 (55). Document what is production (P03) and what is processing and marketing (P15).

Open project page →

AP03 · Local energy system

Working estimate: ~235 (120-350) MNOK
CLC Energy
P04In total

CLC Energy

Nordreisa energy sites

Working estimate
~235 MNOK
Range
120-350 MNOK
Income / yr
~35 MNOK
Jobs
8-25
Maturity
2/5

Main cost items

  MNOK
Pre-project: mapping, energy model, technical assessments 2-8
Pilot phase: local energy production, storage, test 20-80
First energy hub: local heat, microgrid, control system 120-350
Regional CLC model (not counted) 500-1,500

Basis: Slide 43 (cost overview). The working estimate 235 is the midpoint of the first energy hub. Three paying anchor customers are required before construction.

Open project page →

CLC Energy Review / Extension
P18Not in total: Part of P04

CLC Energy Review / Extension

Nordreisa

Working estimate
~8 MNOK
Range
2-20 MNOK
Income / yr
In P04
Jobs
1-5
Maturity
2/5

Main cost items

  MNOK
Energy map, load profiles, ranked measure list 2-8

Basis: Same as the P04 pre-project (slide 43). Not additive.

Open project page →

AP04 · Rovdas housing programme

Working estimate: ~18 (P05 only) MNOK
Rovdas MiniHouse (8 units)
P05In total

Rovdas MiniHouse (8 units)

Rovdas (gnr 13/bnr 172-175)

Working estimate
~18 MNOK
Range
14-22 MNOK
Income / yr
~1.15 MNOK
Jobs
2-6
Maturity
4/5

Main cost items

  MNOK
Per mini-house (60-80 m2 gross area, 2 storeys) 1.8-2.8
8 mini-houses on 4 plots (2 per plot) 14-22

Basis: Slide 45. Income of ~1.15 MNOK/year assumes 8 x 12,000 NOK/month rental; a sale gives a different profile.

Cost check 20 Sep 2026. The slide price equals about 26,000-40,000 NOK/m2 and appears to cover the buildings only. With market prices for small houses plus site services, the check gives roughly 18-36 (base ~26). To be confirmed: are plot, water/sewage and roads included?

Open project page →

Veibakken Two-Storey Housing
P06Not in total: Being redefined

Veibakken Two-Storey Housing

Veibakken (gnr 12/bnr 1)

Working estimate
~29 MNOK
Range
18-43 MNOK
Income / yr
~1.62 MNOK
Jobs
3-8
Maturity
4/5

Main cost items (amounts not yet split)

  • Two-storey houses in a cluster (number not fixed)
  • Terrace apartments (concept image)
  • Roads, water and sewage shared with the Veibakken field (P03)

Basis: The 29 MNOK figure comes from the Rovdas 6-12 unit scenario (9 units), not from the Veibakken concept. A dedicated estimate is needed.

Cost check 20 Sep 2026. The concept image shows roughly 20 two-storey houses plus terrace apartments. The house cluster alone checks at about 28-119 MNOK (base ~70). Not counted in the total.

Open project page →

AP05 · Nordkjosfjellet programme

Working estimate: ~600 (P07 pilot) MNOK
Cave Lodging / WEB3 in the Mountain
P07In total

Cave Lodging / WEB3 in the Mountain

Nordkjosen / Nordkjosfjellet

Working estimate
~600 (pilot) MNOK
Range
150-1,500 MNOK
Income / yr
~120 MNOK
Jobs
20-60
Maturity
1/5

Main cost items (amounts not yet split)

  • Data hall modules (pilot / first commercial module)
  • Cooling, power distribution and security
  • Power and fibre connection
  • Rock hall and access tunnel (see P12, not included here)

Basis: Illustrative, very high uncertainty. Geology, power/fibre and a customer contract can change the frame substantially.

Cost check 20 Sep 2026. No target capacity (MW) is stated. At the Oslo build cost of 12.4 USD/W (Turner & Townsend 2025, assumed 10.5 NOK/USD) 600 MNOK corresponds to roughly 4-5 MW, before rock hall, tunnel and power connection.

Open project page →

Deep-Water Quay & Mountain Facility
P12Not in total: Study only

Deep-Water Quay & Mountain Facility

Nordkjosnes

Working estimate
~40 (study) MNOK
Range
15-80 MNOK
Income / yr
Study phase
Jobs
0-5
Maturity
1/5

Main cost items

  MNOK
Concept selection study / feasibility 15-80
Tunnel, quay, energy and data centre Not costed

Basis: Full development is not calculated. Tunnel, quay, energy and data centre each need a separate business case.

Cost check 20 Sep 2026. The concept drawings show about 7 km of tunnel (4.5 km E6-Nordkjosnes plus 2.5 km to Indre Storvik) and about 0.25 km2 of mountain halls. With PALT's own unit rate for a narrow tunnel (0.2-0.3 MNOK per metre) the tunnel bore alone is roughly 1,400-2,100 MNOK, or about 1,750-2,940 with a concept-stage reserve of 25-40 %. A vehicle tunnel is larger and more expensive. None of this is in the 4,391.6 total.

Open project page →

WEB3 Layer
P17Not in total: Support track for P07

WEB3 Layer

Nordkjosfjellet / digital

Working estimate
~12 MNOK
Range
3-30 MNOK
Income / yr
~4 MNOK
Jobs
3-15
Maturity
1/5

Main cost items (amounts not yet split)

  • Partner, fibre, power and market track
  • Investor memorandum and partner outreach

Basis: Programme cost, no land investment. Supports P07/P12.

Open project page →

SkyWay (Nordkjosfjellet input 25)
P25Not in total: Study only

SkyWay (Nordkjosfjellet input 25)

Regional corridor, route not fixed

Working estimate
~20 (study) MNOK
Range
5-60 MNOK
Income / yr
Study phase
Jobs
1-5
Maturity
1/5

Main cost items

  MNOK
Needs and alternatives study 5-60
Technology and route investment Not costed

Basis: Full technology investment cannot be calculated before a concept choice.

Open project page →

AP06 · Tourism and service nodes

Working estimate: ~40 MNOK
Motorhome Parking Nordkjos
P08In total

Motorhome Parking Nordkjos

Nordkjos

Working estimate
~18 MNOK
Range
8-35 MNOK
Income / yr
~3.2 MNOK
Jobs
3-8
Maturity
2-3/5

Main cost items (amounts not yet split)

  • 20-40 motorhome bays (ground works, marking)
  • Service building: toilets, dump station, water, waste
  • Power, signage and visitor information

Basis: Illustrative capacity estimate. Location and number of bays must be settled against P13.

Cost check 20 Sep 2026. Equals roughly 0.45-0.9 MNOK per bay at 20-40 bays. No benchmark for cost per bay was found, so the figure cannot be verified without an itemised list.

Open project page →

Service Node Input 9 (Straumfjordnes)
P09In total

Service Node Input 9 (Straumfjordnes)

Straumfjordnes

Working estimate
~22 MNOK
Range
10-38 MNOK
Income / yr
~3.6 MNOK
Jobs
3-8
Maturity
2/5

Main cost items (amounts not yet split)

  • 3-6 small cabins
  • Coastal path and viewpoint
  • Simple service point

Basis: Illustrative unit estimate. Assumes seasonal rental, guiding and a simple service point.

Cost check 20 Sep 2026. Bottom-up check gives roughly 8-37 (base ~20). The working estimate is in the right order of magnitude.

Open project page →

Motorhome Parking Nordkjos (variant)
P13Not in total: Alternative to P08

Motorhome Parking Nordkjos (variant)

Reisa Fjæra (gnr 4/bnr 2)

Working estimate
~12 MNOK
Range
5-25 MNOK
Income / yr
~2.4 MNOK
Jobs
3-8
Maturity
2/5

Main cost items (amounts not yet split)

  • Motorhome area with service and signage
  • Activity elements and local products

Basis: Duplicate/alternative to P08. Keep one investment per location.

Open project page →

AP07 · Kvænnes master plan

Working estimate: ~2,783.6 MNOK
Kvænnes Eco-Park, zones 1-3
P10In total

Kvænnes Eco-Park, zones 1-3

Kvænnes (gnr 12/bnr 1), 165,579 m2

Working estimate
~2,783.6 MNOK
Range
2,367-3,970 MNOK
Income / yr
~87.6 MNOK
Jobs
150-730
Maturity
2/5

Main cost items

  MNOK
Excavation and primary support (2.48 million m3 at 400 NOK/m3) 993.5
Design, geotechnics and permits (10 %) 99.3
Shared internal infrastructure 250.0
Processing equipment 140.0
Zone 1 fit-out and technical (8,000 m2) 240.0
Zone 2 fit-out and technical (12,000 m2) 216.0
Zone 3 fit-out and technical (8,000 m2) 360.0
Uncertainty reserve (20 %) 459.8
Working capital 25.0
Total programme CAPEX (base) 2,783.6

Basis: Kvænnes total assessment model, base scenario (range: upside 2,366.7, conservative 3,969.5). Mass handling is modelled to contribute about +295.8 MNOK over 10 years. The excavation price has no contractor quote yet: every 100 NOK/m3 moves the total by about 328 MNOK.

Cost check 20 Sep 2026. The model calculates correctly. Base EBITDA is 11.1 MNOK/year against about 149 MNOK/year needed for an 8 % return on the private capital (assuming 25 % non-commercial capital): a gap of about 138 MNOK/year. The programme needs public or non-commercial capital and is not shown as commercially viable on its own. The 730 upper jobs figure is not explained by the operating budget, which carries at most about 96 full-time positions.

Open project page →

Naturarv Nord (Kven institute)
P11Not in total: Part of P10

Naturarv Nord (Kven institute)

Kvænnes / nature zone

Working estimate
~90 MNOK
Range
35-180 MNOK
Income / yr
~18 MNOK
Jobs
10-30
Maturity
2/5

Main cost items (amounts not yet split)

  • Exhibition and cultural centre
  • Language and course rooms
  • Culture trail

Basis: Illustrative working estimate. Included as a function within P10/P16, so it is not added again. Public or non-profit funding is likely.

Open project page →

Preparedness (Beredskap)
P14Not in total: Part of P10

Preparedness (Beredskap)

Kvænnes area

Working estimate
~45 MNOK
Range
15-100 MNOK
Income / yr
~8 MNOK
Jobs
5-15
Maturity
2/5

Main cost items

  MNOK
Tunnel and mountain-facility system (concept, not costed) Not costed

Main cost items

  • Helipad and drone hub
  • Support functions for preparedness

Basis: The 45 MNOK working estimate covers the helipad and drone hub only. The tunnel and facility figures on the page are draft planning figures.

Cost check 20 Sep 2026. The helipad/drone hub does not appear in the Kvænnes zone 1-3 model, so it may not be inside the 2,783.6 total. See P12 for the tunnel system, which is not costed.

Open project page →

Domes at Kvænnes
P16Not in total: Part of P10

Domes at Kvænnes

Kvænnes

Working estimate
~60 MNOK
Range
25-120 MNOK
Income / yr
In P10
Jobs
0-5
Maturity
2/5

Main cost items (amounts not yet split)

  • Overall plan and facilitation

Basis: Planning and facilitation phase overlapping P10. No separate build cost.

Open project page →

Kvænnes Area Input 19
P19Not in total: Part of P10

Kvænnes Area Input 19

Kvænnes

Working estimate
~15 MNOK
Range
5-35 MNOK
Income / yr
~3 MNOK
Jobs
3-10
Maturity
2/5

Main cost items (amounts not yet split)

  • Programme and smaller premises: courses, meeting places, first aid

Basis: Illustrative estimate. A programme/operator function under P10, not a separate large building investment.

Open project page →

AP08 · Tourism and community strategy

Working estimate: ~25 (not counted) MNOK
Strategy Input 20 (tourism programme)
P20Not in total: Programme

Strategy Input 20 (tourism programme)

Nordreisa (non-areal)

Working estimate
~15 MNOK
Range
5-40 MNOK
Income / yr
~3 MNOK
Jobs
3-10
Maturity
2/5

Main cost items (amounts not yet split)

  • Product map and joint booking logic
  • Three sellable year-round packages

Basis: Programme cost. Physical investments sit in the individual projects. The AP08 figure (~25 with P21) is not counted in the total.

Open project page →

Strategy Input 21 (Polar Arena framework)
P21Not in total: Framework

Strategy Input 21 (Polar Arena framework)

Nordreisa (non-areal)

Working estimate
~10 MNOK
Range
3-25 MNOK
Income / yr
None (enabler)
Jobs
1-4
Maturity
2/5

Main cost items (amounts not yet split)

  • Ten-page framework document: goals, principles, map, portfolio steering

Basis: Strategy, design and anchoring. No direct income.

Open project page →

AP09 · Winter infrastructure

Working estimate: ~15 MNOK
Winter Offer (snowmobile trails)
P22In total

Winter Offer (snowmobile trails)

Nordreisa winter arenas

Working estimate
~15 MNOK
Range
5-35 MNOK
Income / yr
~1.5 MNOK
Jobs
2-8
Maturity
3/5

Main cost items (amounts not yet split)

  • GIS-based route matrix with conflict level per stretch
  • Signage and marking
  • Safety measures

Basis: Illustrative plan/infrastructure frame. Commercial income is limited; societal value is central.

Cost check 20 Sep 2026. 15 MNOK is not itemised and looks high for planning, signage and safety, against about 1.5 MNOK/year income. A component list is needed, and it may be a municipal planning task rather than an investment.

Open project page →

AP10 · Veibakken experience area

Working estimate: ~120 MNOK
Gudepark
P23In total

Gudepark

Veibakken

Working estimate
~45 MNOK
Range
15-100 MNOK
Income / yr
~7.5 MNOK
Jobs
5-15
Maturity
2/5

Main cost items (amounts not yet split)

  • Landscape-based nature and culture trail with seven theme zones
  • Discreet installations and interpretation
  • Pilot with 1-2 zones before the full park

Basis: Illustrative low-impact phase estimate. No quantities yet.

Cost check 20 Sep 2026. Cannot be verified without quantities. The 45 should be tied to the 1-2 zone pilot, not the full park.

Open project page →

Polar Arena Veibakken
P24In total

Polar Arena Veibakken

Veibakken

Working estimate
~75 MNOK
Range
25-180 MNOK
Income / yr
~15 MNOK
Jobs
8-25
Maturity
2/5

Main cost items (amounts not yet split)

  • Year-round activity and outdoor centre, phase 1
  • Parking, safety and area works

Basis: Illustrative phase-1 estimate. Coordinated with P23 on land, with a separate operating model.

Cost check 20 Sep 2026. The minimum product and floor area are not defined, so the figure cannot be verified until a space programme exists.

Open project page →

  • Figures come from the PALT rough-calculation model (Grovkalkyler), the slide deck for the 25 inputs, the Kvænnes total assessment model and the tunnel cost brief of 10 Nov 2025.
  • All amounts are MNOK, 2026 price level, excluding VAT, financing, land purchase and extraordinary ground conditions, unless stated.
  • 'Cost check' boxes compare the working estimate with a bottom-up estimate using market references (residential building cost 2026, Norwegian water parks, Turner & Townsend data centre cost index 2025) and stated assumptions.
  • Cost per motorhome bay, greenhouse/aquaponics per m2, snowmobile trails and helipad cost were not verified: no source was found.
  • All figures are working estimates, not approved budgets, quotes or a financing commitment.